Track work with tasks

Plans
Every plan
Where
Risk Register
Updated
Checked on
v0.41.2

A task is one piece of work with an owner and a due date; open it on a risk to show what brings that risk down, or on no risk for anything else.

Where tasks live

  • The Tasks panel on a risk's page lists the tasks on that risk.
  • The task register lists every task, on a risk or on none. Open it from Every task, on a risk or on none → on the Risk Register. Its headline answers the main question, for example "1 open task is past due.", above five figures: Open, Past due, Unowned, On no risk and Done.

Open a task on a risk

  1. On the risk's page, in Tasks, select Add a task.
  2. Fill in Task (required, up to 200 characters), Severity, Owner and Due.
  3. Select Add the task. The page says "Task added." and the risk's Tasks figure counts it.

Open a task from the register

  1. In the task register select New task.
  2. Fill in Task, Severity, Owner, Due, On the risk (or no risk), Related control and Description (up to 20,000 characters).
  3. Select Open the task, or press Enter in the Task box. The task's own page opens.

Change a task

  • Status: choose not started, in progress, resolved or closed. It applies at once, with Undo for a few seconds. In the Tasks panel on a risk's page the same status not started reads open.
  • Edit the task changes every field, including On the risk: move a task onto a risk, to another risk, or to no risk.
  • Each task page has its own comments and files.

A task past its due date shows "Past due since" the date in red, on its page and in the register.

Find tasks

The register's chips switch between Open, Not started, In progress, Resolved, Closed and Every state. Filter by severity, On a risk or not and Sort tasks narrow and order the list, and Search tasks matches titles, owners, risks and controls. The page address keeps your choices.

Act on several tasks at once

  1. Tick the box beside each task, or Select this page.
  2. Choose Resolve, Close or Delete.
  3. The bar names what will happen, for example "Resolve 3 tasks? Each is marked resolved, dated today unless it already was." Select Yes, resolve 3, or Keep them.

The bar reports the result, such as "Resolved: 3 tasks."

Delete a task

On the task's page select Delete, then Yes, delete. Its comments and files go with it; the records it tracks stay, unlinked from it. Only owners and admins can delete.